HORIZON MIGRATION TIMELINE
EFFECTIVE DATE |
ACTIVITY |
DESCRIPTION |
WORK GROUP AFFECTED |
4/23/03 and forward |
AUTHORITY changes / deletions stop |
YOU MAY NOT: YOU MAY:
|
Technical Services |
4/25/03 and forward |
BIBLIOGRAPHIC & ITEM changes / deletions stop |
YOU MAY NOT: YOU MAY:
|
Technical Services & Public Services |
4/28/03 and forward |
PATRON DELETIONS stop |
YOU MAY NOT: YOU MAY:
|
All Library Staff |
5/22/03 and forward |
GAP LOAD = All activity other than circulation stops |
YOU MAY NOT: YOU MAY: |
All Library Staff |
5/26/03 thru 5/28/03 |
CIRCULATION CUTOVER = ALL ACTIVITY CEASES |
Library Closed |
All Library Staff & Patrons |
5/29/03 |
LIBRARY GOES LIVE ON HORIZON! |
Library Re-opens |
All Library Staff & Patrons |